Featured Projects



Wimbledon
Indoor Court


A model was created to be used in conjunction with the logistics plan to show how cranes, MEWPS and spider cranes would be used to aid in the construction in the different phases of the project.
  • Kaicer Building Envelope Solutions
  • Roofing and cladding cost £70 million




Court 1


Visuals were created to be used in conjunction with the tender package to showcase the construction of the cladding system and Kalzip roof.
  • Lakesmere
  • Roofing and cladding cost £80-£100 million
  • Sections of the new roofing & cladding system